Monday, March 4, 2024

Rough...and not quite ready


Been a minute, I know...I was away all last week, and, a fair bit has transpired since I last posted.

The house is ready for a "rough in" inspection.   This check on all the infrastructure precedes insulation and then drywall.   It was to have taken place a week ago Friday.  I was at the airport awaiting boarding my flight that morning when my contractor pinged me and asked if I could talk.  Turns out the inspector won't do the rough in inspection because, yes, there's another stamp on the plans that's in the way.

So this falls into the category of the roadmap not being available or transparent.  When we got the plans, you may remember there were a bunch of stamps on it.



This time the nemesis is the stamp placed by the Fire code enforcement folks which says Fire Sprinklers are required.  They're not.  Fortunately, back in 2017 when the first big fire storms hit the State, we had a piece of legislation passed in support of rapid building and rebuild of housing that exempts ADUs of less than 1200 sq ft from the sprinkler requirement if the existing structure on the property is not required to have them.  That is the case in this instance, but it seems to be that the County is saying "prove to us you don't require them and are exempt" vs them checking in the first place and not putting this requirement on the permit. 

When we received this, I noted that and knew that I would need to clear it up before getting final sign off.  Silly me.  It turns out it needs to be cleared up NOW because naturally an inspector who sees that on the plans won't do the rough in inspection if sprinklers haven't been installed.  An amusing side note of nostalgia on all this...the legislator who put this into motion is Bob Wieckowski, with whom I worked while on staff at Congressman Don Edwards' office, who is a Fremont home town guy who ultimately got elected to City Council and is now State Senator.  Thanks Bob!

Getting this news as I'm getting on a plane meant that it couldn't be dealt with for a week - so everything's been pushed back until I returned and I'm going to the County tomorrow to clear it up.  😒  So much for my get out ahead of it strategy!  The working assumption now is if I can get that taken care of tomorrow, we'd have the rough in inspection by the end of the week and get insulation set up for next week.  🤞🤞🤞

In the meantime, trimmings have been proceeding at the house.  The big double doors are all installed!  Made some last minute switch ups in the plan on that but, it all worked out great.

The installation of the doors allows for the siding to be installed on those panels, it all looks so much more intact now!  The one set of doors that is white didn't come in the same trim color but I got the paint formula for the trim and it'll be painted to match outside and the inside will be painted to match the interior walls...pretty sweet.

It's cool to see and experience the space with all the light that the doors provide!  It's becoming!

Doors from kitchen out to covered patio

Doors in my bedroom
Doors in the bathroom...the shower will be what's in front of those doors.
 

While I was away this week I was able to make progress on a bunch of things...things that I've been noodling on and carrying mentally for a long time...so happy to have these off my "to do" list!  First of all, the local appliance store, Asien's, that has been in business here for decades, shuttered abruptly and unexpectedly two weeks ago.  I had quotes from them for my fridge, cooktop and dishwasher and fortunately, did not have an order placed with them - lots of other people are way more stuck than me with this development.

I immediately got to sourcing alternatives and boy did I get lucky!  I was able to get my dishwasher, fridge and washer/dryer tower from a wholesale outlet saving over $2500!  And I got my cooktop from a place in NY that saved me about $600 so feeling pretty good about where all that landed.  Not only that, but they'll hold the appliances until I'm ready for them...wohoo!

I also found a hot tub!  Super excited about landing this deal...my hot tub lifestyle makes that element a necessary one for my well being.  The one I've had since 2008 has done its time, I've moved it twice and I don't think it can withstand another move.  Getting another one, however, is a sticker price shocker to say the least.  I managed to get connected to a shop near me that takes hot tubs when people swap them out/upgrade and they replace all of the electronics, put in a new pump and ozonator and give you a fresh lid and new chrome jet covers...basically rebuild the thing, and sell them for half their retail price.  I found the perfect unit, in a price range I could say yes to AND they are giving me money for mine and taking it away to boot!  SCORE!

On a good trajectory - keeping the process flowing...working next on the carport design, and finalizing the etched glass front door purchase....we are on a ROLL!





 



Monday, February 12, 2024

WIRED!

I was in Seattle last week so wasn't on site for the day to day progress but truthfully, it's all been electrical.   Alex with Denny's Electric (the guy I shut into the house!) has been amazing.  Once again, things are way more complicated and involved than I could ever imagine - and his skill and competency are pretty awesome to witness - super glad he's on the team!

I honestly don't feel like I have that much going on in this little space and yet, you'd never know it from the wiring!  Wires through the walls, strung through the trusses in the ceiling, within the wall structure, you name it.   




I'm not doing any install of media wiring, choosing to keep things simple. I'm not wiring for sound, internet or cable.  I am likely to use Starlink (have to make peace with giving Elon Musk's company money...not starting there but preparing for what may be inevitable for connectivity in this rural area) and the blue chaser in this image is the infrastructure to support that when/if I install it.

Next is the rough-in inspection and then we get to do insulation!  The doors arrived last week so they'll get framed in and then they can complete the siding on those panels as well.  If we are successful with an inspection this week, insulation should happen within the week and then drywall last week of the month!


 

Sunday, January 28, 2024

Moving swiftly - and it had consequences! 🤦🏽‍♀️

This week was a rapid succession of lots of little and not so little things.

The A/C splits were roughed in...the plans had called for ceiling mounted units which would have been really much more aesthetically pleasing than white boxes on the walls..however, it turns out you can't install ceiling mounted units on a sloped ceiling.  So, we pivot to wall mounted units, of different BTUs in each location...6k for the Zen Den, 9k for the bedroom and 16k for the living space.  Another letting go, adapting moment!

There will be one condenser outside for all three units.

Met with the electrician to finalize the install plan.  Learned that the materials and install cost for the interior perimeter lighting I had hoped to utilize was $8700 so we won't be doing that!   We have a DIY alternative that will suffice, and we validated where all the switches and outlets would be and I got to pick the face plate color!  Wohoo!   Going with Ivory, FYI.

The plumber realized that the hybrid hot water heater required both venting and pan drain that he had anticipated putting through a wall that is drawn into the plans but will ultimately have the murphy bed in it, so plumbing can't run through it...that glitch is a function of the County's seeing that room as a bedroom and requiring, hence, an egress, but we can't make that happen cuz the exterior walls were already built and can't be modified.  So we built a solid wall where the murphy bed will go and will install it after we get our final clearance on the building permit.  Yes, these are the machinations that go on constantly.  They had to cut into the slab to run a line out of the house under the rebar...kinda painful to see because as you may have seen in earlier posts..that slab was perfection.  It's not a consequential thing and can be easily remediated but it's the fact of it, that it had to be cut into.  Anyway, in the course of all that sorting out, we realized we could save on the venting system by having louvered doors on the laundry room  - if you have louvered doors a vent is not required, so that was a good catch!

Met with the cabinet maker, and refined the cabinetry plan - so great to have the benefit of those who know and have vision beyond my thinking.   Shifted a couple of things and confirmed measurements.  Really like where we ended up, waiting on that estimate.

Found a sink!  I have wanted to use reclaimed materials as much as is realistic and was out and about on Friday and went to one of the sources for reclaimed goods and found the perfect kitchen sink, a pretty high end brand that was unused, color perfect and I got it for half its original price.  Yay!

That day I also just stopped in at Home Depot to grab an additional sample of my Cesarstone quartz countertop I'm using and saw it was at a lower price than my original estimate and there was a 10% off promotion that expired the next day so made that purchase too!

Next week the electrical work will get done and we move on to insulation.  Will do a walk through with the electrician on Monday to confirm all the switch and outlet locations.   Here's a funny story that prompted the 🤦🏽‍♀️ in the post title....I stopped by the house on Friday to drop off the rain chains that were delivered so the roofer could install them.  When I went in, Alex, the electrician doing the work was there, I met him and then I left.  Later that afternoon I had a meeting with Joe at Denny's Electric (the owner) and he told me that Alex called him because I LOCKED HIM IN!  I seriously cannot believe I did this but when I got there the door was closed, so when I left I robotically made sure I closed it, and latched it!  Oy gevalt.



Helluva way to meet the owner eh?!!  Sheesh....a reminder to slow down, for sure.

 

Sunday, January 21, 2024

She has a chapeau!

Abel Martinez, the roofer, and his team have at last completed their task with the metal roof installation!  They were to have started the week of December 18, and taken a few days, but construction issues and the weather have drawn this job out inordinately long.   I'm grateful for their persistence and dedication to the quality job they've done.



They work rain or shine, and to watch them scamper around that slick metal roofing is a tad unnerving I must say!  They use several different resources that keep them from sliding down the panels, amazing to watch and it's evident they pitch their bodies in angles to the roof line that support balance, etc...such skill.

They fashioned a sweet little cap to the roof - the house was to have had a more substantive cupola, a feature I looked forward to but have abandoned.  Initially the plans called for batt insulation in the ceiling which requires venting and the cupola would have been a part of that venting system.  I have since decided to do spray isoprene insulation in the ceiling - it's a tad more expensive but it eliminates venting, which is an even more fire safe choice. That, along with the labor involved in constructing the cupola, and the equipment that would have been required to mount it...for something purely aesthetic, nope.  So instead I get this sweet little feature they made for me at the top:


The only task that remains is to install the rain chains I'm using in lieu of downspouts...that'll happen within the week.

Inside...plumbing is just about done!


 

Electric work begins this week so things are moving at a pretty consistent pace....

My prediction, and my mental adaptation I'm doing at the moment, is that the house will likely be completed but I will not be able to occupy it because it's highly probable the septic system would not get in before that time...we are having SO MUCH rain here.  Much needed and it is the determiner of when the septic can be installed...so yah, I can foresee the house in a state of readiness to be final inspected but not be able to until nature allows the septic system to get in. 

Just sayin'.....there's little that's reliable with respect to timelines and timeframes!

 

Friday, January 12, 2024

It's mostly an inside job...

If you were around this week you might wonder if anything was happening...and it was.

The porch roof extensions are finally ready for roofing.  The WUI (Wildland Urban Interface) area I'm living and building in has adopted a bunch of new requirements for materials and expectations of fire resistant (I believe that's a bit of an exaggeration but I digress) building processes so the porch work took a few extra steps - this picture may not look terribly different from the last one, but it is, and she's ready!

Roofers come back on Monday and she should be completely sealed up next week!

Meanwhile, on the inside...framers completed their work and we made some adjustments to the original thinking on a few fronts.   Good stuff to have identified now, like adding in blocking between the beams where I'll likely be hanging things so there's more supportive infrastructure and we don't have to hunt for studs in the walls.  We added a pony wall in the bathroom for between the shower and the vanity that will let me have the shower controls outside the shower so I don't have to step in, turn it on and maybe get wet with cold water before it's ready, that kind of thing.

The plumber is on site, getting the pipes in, vents in, and we picked out the locations of the hose bibs on the exterior.

Found out that the A/C split units in the plans that are ceiling mounted, which was a great aesthetic option so there would not be the white boxes on the wall that are typical, can't be installed in a sloping roof..so shifted that plan as well...

So we're at that level of activity and decisions...electrician comes next week to walk through and validate everything and they'll get going on the wiring.  

A great gift of the week was when PG&E called to tell me that there's nothing more required for them to convert to permanent power, so we are DONE!  I had put down a $2500 deposit for the engineering to determine what level of power supply and infrastructure was required to support the ADU given the existing transformer on the property.  (You may recall the events when temp power was installed that set this all up favorably -see the blog post from October 12).  So now it's just an administrative change of status and a refund of the deposit...yippee!

I'm going to be traveling Sunday-Wednesday of this coming week so won't get to watch the metal roof install but I'm sure Jean will snap some pics for me.  Every day a little closer....

 

Friday, January 5, 2024

Taking its shape

This week the team made a lot of progress on the roof extensions over the porches - the rain held off enough to get as far as this:




Little by slow, it becomes more and more....rain coming tomorrow so the hope is that they can get the plywood on in the early part of next week so the roofers can get back and finish the metal roof install - we might get lucky and have that done by the end of the week.

This week also saw progress on the wall framing in the interior...fascinating to watch.  Pretty much everything is more complicated and involved than I could have known.  After the studs are all in place, furring tape is applied in however many layers it takes to get the wall precisely level.  Again, I so admire the work the framing crew is doing....they installed plywood where it's called for as well..here's the interior as of today:




Next week plumbing and electric get going on the interior and the install of the A/C split units will be next.  My architect is coming to talk about the carport we need to design to get that permit process going.  The solar panels will be mounted on the carport and being ready in the next month or so needs to start now.

I'm spending a fair chunk of time in the materials decisions territory - I have had things chosen for, oh about a year and a half now (!) and reality meets the moment so reconsiderations abound.  Doors, for example...I need 3 sets of exterior doors, was intending to do french doors.  Turns out those are all about $4-5k each so I'm making room for the possibility of sliding doors instead which are about a quarter of that cost...I'm guessing you get the picture...it's kind of endless in this realm.  I'm doing my best impersonation of adaptability, some days it looks good on me, other times I drift into full blown "what was I thinking?!!!" territory with respect to the whole project. 

One foot in front of the other...that's the only way it works for me, taking the steps in full recognition of the insecurities that lie beneath each decision....

Onward.

Friday, December 29, 2023

Dancing with the Rain

Not singin' in the rain, not doing a rain dance....just, dancing.

The weather is a bit in charge still, and she is only sort of predictable.  This week she precluded more advancement on the exterior work but the interior work really took off.

Still trying to get the porch overhangs done, so the metal roofing can be installed.  There was another part glitch this week...there is some hardware, technical term "buckets", that are used to hold/affix the beams across the patio overhangs.  The brackets are fabricated with left or right facing orientations.  For some reason we got three rights and one left, and needed two of each.


 

This solutioning team got on it, first exploring with the local welding shop if they could reorient one of the rights to a left.  Meanwhile I reached out to Deltec to see if they had a replacement part they could expedite our way.   All initial inquiries suggested we wouldn't get anything for over a week.  Deltec was awesomely responsive, during this mostly holiday week for folks...it just sucked to imagine another week waiting on this part.   Then, yet again, grace came our way and yesterday afternoon we got a text from the local welding shop, they had done the work and the part was ready to be picked up!  I immediately went and picked it up and we're back in business.  Now if the rain would just pause for a hot minute to get 'er done!

The interior work...so cool.  Here's a dramatic/panoramic shot of the framing:


Can't even describe what it's like for the drawings to go 3D like this...to stand in a space, to begin to feel its dimensions.  Kinda cool too to get to see the bones...when else would you get this glimpse of the inner workings of a place?  


The roofers - they're another breed.  They work rain or shine...they started the metal roof install, and they put the fascia up.  Again, so relieved I like the color of the metal roofing and it's not something I'll cringe over forever!!  Can't wait to see the final pattern but it's a cool preview of coming attractions right now:



The long slow pull forward continues...and so does the rain.  We're getting a deluge today, more next week...

It's exactly a year to the day that we submitted the application for the building permit.  What a wild year of waiting, nudging, patience, strategery, and overall glorious collaboration. 


Friday, December 22, 2023

The Jig is up..no, actually it's OUT!

Not a lot of visuals for this week but a LOT was accomplished.  There was, as reported, lots of hardware to install to secure the shell to the foundation and fully secure the roof trusses.  With that done, the jig came out!

Remember, it's the pole that held up the collar to which the roof trusses were secured.  Here's some glimpses of that, now:



The open collar will be capped at the base with an engraved tile...a local friend Jim Strand does etching on tiles and he's gonna create something for me that I can mount, with a bit of a gap for lighting...should be cool!

Next week will involve beginning to frame up the walls in the interior and finishing the porch overhangs so the metal roofing can get on.  Here's a quick look at the layout on the floor, super cool to see, and stand in each space!!


 


Another thing the crew did is create plywood doors to close the door openings.  Mostly my ask, as I don't want to lay out a welcome mat for wildlife and give those future neighbors the opportunity to learn new habits involving being in the interior that I'll have to effort to undo later!

So, into a holiday weekend we go.  In the meantime, today was starling swarm day!  Check out the views, and the action, this afternoon of the flocks in flight...totally mesmerizing!


 

Saturday, December 16, 2023

Fortune smiled upon us again....

Well, we did it.  It was a nail biter of a week, not gonna lie, but in the end, everything ended where we needed it to.

The plywood on the roof was completed, and here are some groovy images of all that:





The solar permit application was submitted by end of day on Tuesday.  We called for an inspection which happened on Thursday and by 2p Thursday afternoon we had passed inspection and the roofer was putting waterproofing on the roof!  The work concluded this morning...here's what she looks like all buttoned up for the impending rains. PHEW!

Metal roofing was to have been installed next week but we havea lot of steady rain forecasted so the when of that remains a bit in flux.  The patio covering roof extensions need to get on the roof and that can't happen till the rain subsides as well..so again nature is a bit in control but at least we have a water tight structure!!!


Now interior work can proceed which, after all the structural elements are installed - there's a bunch of hardware to secure this thing to the foundation - metal strapping, hold downs, etc - look closely at the metal strips running down the 2x6 boards at the end of the panels, that's about 50 nails (maybe more!) to secure each one and the metal brackets at the bottom are the hold down hardware that also get secured, along with the strapping at the top - they'll be able to move on to framing interior walls.

As usual there are emerging developments that need solutioning...the team has been stellar in problem solving and ensuring the work arounds don't compromise anything engineering would take issue with.  

I've been finalizing materials sourcing, getting doors lined up and my flooring I had chosen sold out so I'm on the trail for another and so on...it's ALWAYS something!

So grateful for where this ended up - nothing about it was guaranteed and this team really worked together to make it work -continued abundant gratitude on my part.



Monday, December 11, 2023

Put a cap on it!

So this week is all about getting the structure ready for the metal roof.  Lots of little and big things need to happen for that to be the case and, some bureaucratic wrangling just for fun.

Plywood is going on the roof, and since the parts come pre-cut, it moves pretty quickly.




There was a lot going on in the inside, too. Less visible/capturable but it's all related to securing the structure - lots of hardware to install to anchor the panels to each other, the slab, etc.  Right now, it's partially covered and kinda wild shift from the trusses being the visual magnet to now, feeling tucked in.




Once all the plywood is on the main structure, they'll begin to get the porch overhangs installed.  

In the meantime, in permit land....so all new builds in CA are required to have solar panels.  The extent is partly determined by some energy calculations done on the structure but it's just a baseline minimum.  I have been imagining doing solar mounted on the carport to provide resiliency (e.g. battery storage of power for outages) that will be constructed later - so I punted the arranging of solar into 2024 mentally.  HOWEVER, my approved plans have a little stamp on them that demands otherwise:

Why there is an interdependency between having solar lined up and conducting an inspection on the roof nailing is a tad mystifying - especially since I'm not intending to do roof mounted solar - however I've been told, or it's been suggested, that it's the County's way of prompting action on solar as many people punt that out in the future, sometimes for years.  OK, but I need a roof diaphragm inspection THIS WEEK so my metal roofing can get on next week and we are water tight for rainy season!

So I hustled and got a solar plan engineered and designed, and the company will file the permit application but the guy who does that was on vacation since thanksgiving and it hasn't been filed - and he comes back from vacation tomorrow.  So I'm once again hoping that we will prevail and everything will line up - which would require the grace of acknowledging we have a plan and are moving on it but won't likely have an approved permit this week.  Fingers and toes crossed they'll allow the inspection to proceed - for its reasonableness - and we can stay on track but these are among the things out of anyone's real control.

Never a dull moment.

Here's where we ended up today - less likely to do daily posts as we head into a different rhythm of work but will certainly update as progress is made!