Thursday, October 12, 2023

Fill 'er up!

This week moved the foundation process dramatically forward.  The day after the footings were poured, the form boards came off and it is now possible to really see the future space of the house.

The next task was setting up the form boards for the patios and stem walls.  The North patio was first, it having the larger stem wall.  Same process as the footings - trench dug, form boards placed and rebar dropped in.


 

With that in place, they moved on to the south side, where the entryway will be.  Trench and forms there too with rebar.


 



All the while, the fill for the slab is being laid down.  It's multi-layered...there's a fabric that goes down, then sand, then rock and it's all compacted.  The plumber still has to lay down pipes and then they put a final layer over and it's ready for pouring.  





SO great to have skillful people, good people doing good work.  Monday the plumber will come and lay down the pipes, we'll have an inspection on the rebar in the patios and they'll pour concrete on Tuesday for the patios.  The slab will get finished and be poured as soon as it can be...wohoo!!

Oh, and on timing, we have confirmed we will be sending for the shell to arrive the week of November 27.   That's when, as they say, shit gets really real.

Does not suck to gaze out at that scene....

And the winning number is......4511!

A new address, another step into the realm of the reality of it all.  My new home will be located at 4511 West Dry Creek Road!   It's kinda funny to me that I'm moving from 2311 W Dry Creek to 4511...no need to wonder how far down the road I will be, eh?!!!

The big deal about getting the designated address is I can now get power to the property.  I've mentioned before the temporary and permanent power paths - both are activated, but in order to move forward on the permanent power project, the address is required.  In the meantime, my BFF at PG&E, Omar, got my temporary power scheduled for activation today.  

It was a big day at the site...PG&E first showed up and did as much setup as they could however the existing power pole from which they'd extend the line to my site has a transformer that is not only antiquated, it was leaking.  He could not make the connection.   The good news was that he then put this project into emergency status for a transformer replacement and upgrade and it actually happened TODAY!  


Everyone loves to bash PG&E and I understand there are a lot of ways they can improve but I'm telling you, these guys were skillful, graceful in the task, communicative, and just really decent guys.  They arrived an hour after the request was put in (shocking) and it took about 4 hours to get things set up.   So, in a nutshell, we now have power.  Not only that, but they upgraded the transformer so we may not need to upgrade again for permanent power...remains to be seen but today was a really fortunate day.

I've got a mailbox ordered, and we're going to upgrade the mailbox post at the end of the driveway that now holds 4 mailboxes, soon to be 5!