Saturday, October 21, 2023

Almost there.....

All systems are go!  We are on a glide path to slab, AND, the septic permit was issued last week so we are on our way to major infrastructure completion.

 

The race is on to get that system in before bigger rains, and to get the slab poured as well.  We are looking at a few weeks of good weather so no imminent threats of rain...so far. 

The patio footings have been poured and are awaiting filling.  The guy in the yellow shirt in these images has more upper body strength than I have in my whole body...he holds, directs, lifts that hosing FILLED with concrete and moves it where it needs to go with such precision...








Those are just the footings.  The patio sections need to be filled with sand, rock, fabric just like the main house pad.  Before all that can be finalized, including the main pad, the plumbing had to be dropped in and stubbed up above the level of the final slab pours.   

Look at all the piping in this picture!  This 1000 sq ft home has three sinks, one toilet, a shower, a hot water heater and a washing machine needing water and wastewater connections.  It looks like the london tube map to me!!!  😂

 


There'll be another inspection of the utilities (water and elec) on Monday, then final fill and rebar are installed and the slab pour should be Thursday of next week!  The patios will follow, either the day after or soon...

An update on the shell delivery, we had to bump it to the week of December 4.  Knowing the when lets us plan all the subsequent steps but...don't tell anyone, I could be living in this house by March!  😲

In the meantime, the latest quote on the port-a-potty:

 


Until next week....thanks for glancing in this direction and coming along for the ride. 💓

Thursday, October 12, 2023

Fill 'er up!

This week moved the foundation process dramatically forward.  The day after the footings were poured, the form boards came off and it is now possible to really see the future space of the house.

The next task was setting up the form boards for the patios and stem walls.  The North patio was first, it having the larger stem wall.  Same process as the footings - trench dug, form boards placed and rebar dropped in.


 

With that in place, they moved on to the south side, where the entryway will be.  Trench and forms there too with rebar.


 



All the while, the fill for the slab is being laid down.  It's multi-layered...there's a fabric that goes down, then sand, then rock and it's all compacted.  The plumber still has to lay down pipes and then they put a final layer over and it's ready for pouring.  





SO great to have skillful people, good people doing good work.  Monday the plumber will come and lay down the pipes, we'll have an inspection on the rebar in the patios and they'll pour concrete on Tuesday for the patios.  The slab will get finished and be poured as soon as it can be...wohoo!!

Oh, and on timing, we have confirmed we will be sending for the shell to arrive the week of November 27.   That's when, as they say, shit gets really real.

Does not suck to gaze out at that scene....

And the winning number is......4511!

A new address, another step into the realm of the reality of it all.  My new home will be located at 4511 West Dry Creek Road!   It's kinda funny to me that I'm moving from 2311 W Dry Creek to 4511...no need to wonder how far down the road I will be, eh?!!!

The big deal about getting the designated address is I can now get power to the property.  I've mentioned before the temporary and permanent power paths - both are activated, but in order to move forward on the permanent power project, the address is required.  In the meantime, my BFF at PG&E, Omar, got my temporary power scheduled for activation today.  

It was a big day at the site...PG&E first showed up and did as much setup as they could however the existing power pole from which they'd extend the line to my site has a transformer that is not only antiquated, it was leaking.  He could not make the connection.   The good news was that he then put this project into emergency status for a transformer replacement and upgrade and it actually happened TODAY!  


Everyone loves to bash PG&E and I understand there are a lot of ways they can improve but I'm telling you, these guys were skillful, graceful in the task, communicative, and just really decent guys.  They arrived an hour after the request was put in (shocking) and it took about 4 hours to get things set up.   So, in a nutshell, we now have power.  Not only that, but they upgraded the transformer so we may not need to upgrade again for permanent power...remains to be seen but today was a really fortunate day.

I've got a mailbox ordered, and we're going to upgrade the mailbox post at the end of the driveway that now holds 4 mailboxes, soon to be 5!

Tuesday, October 3, 2023

She's not going anywhere.....

 Today was a BIG day.   It started peacefully enough, sunrise over the valley, cool temps...



The plan for pouring the foundation footings was for three cement trucks, each loaded with 8 yards of mix to keep the truck lighter given the impact of the weight on the driveway plus it's a bit steep and it's not good to have the concrete on a slope cuz it'll try to pour out of the truck apparently!  The setup involves a truck and a pump - and those guys jockeyed those rigs amazingly smoothly on a narrow driveway, it was like watching synchronized swimming!

A bit of a visual aid for the point about weight - check out these tires, that should give you a clue as to the weight of the load - they're not flat by the way!


The truck pours concrete into the pump that send it out to the foundation in a big giant hose..the guy who handled that is unbelievably strong, and deft!




It's poured into the form boards and oozes out to fill the trench below.  It's over filled, then another tool is used to pump air down into the muck so it all condenses down and compacts.

Next, they come along and smooth over the surfaces by hand.


And they keep going, until they get all the way around.  There's another tool, looks a bit like a jackhammer, that vibrates and it helps keep the form boards exactly where you need them after the concrete goes in and tries to widen them out.






It's really like watching a great ballet or something...they are so smooth in their movements, so skillful in the task.  And in the end, we get this:

They remove many of the supporting boards so they don't get fixed into the concrete and tomorrow all of the form boards will come off.  It'll be a concrete foundation ring!


I can't think of a more dramatic image of the slope!  It's look more level by the day to my mind's eye.  Can't wait to stand on the slab that will be poured into the middle.

It only took about two hours for the pour, a bit more to finish up.   That house is not going anywhere!  Next, the footings and support for the side patios will be framed up and readied for pouring which we hope can happen in conjunction with the slab pour.  Plumbing has to get their pipes in and walls have to be mapped out for the stubbing up of water and wastewater pipes before the gravel and sand can be put into fill up the interior and be ready for a slab.

Stay tuned!

Friday, September 29, 2023

Fast Forward!

I suppose that may be a relative term but oh my this week a lot got done!  

The rebar came into the scene next, not only the cages at the base of the foundation but all of the rebar that will connect the slab to the foundation.  Each of these rods will be bent over once it's time to pour...

 


Pipes were cut into the form boards to accommodate the wastewater egresses, the electric that needs to run from outside->in and vice versa and to provide for "seep" from under the foundation.   

 

The electric conduit is laid down, and mapped to the places in the house where it's needed with the main panel setup being near the front door.



 I just get giddy wandering around this site!  Seriously this STILL so does not look level to me:


And yet, it is:

 

Today a County foundation inspector came, and the guys had to wait around in a 4-hour window...I brought sandwiches and we sat on my picnic bench under the oak tree...a really beautiful clear air day today...I have such deep respect for their expertise - they are good people with great talent and I remain so grateful for their being on the team.  The inspection passed. 

This week's port-a-potty adornment, therefore, is:

 

In continuing good news, Omar, one of my PG&E BFFs notified me temporary power was approved!  I went today and got the necessary temp and private power pole permits and set up the required inspection for Monday.   My other PG&E BFF, Brandon, who is handling my permanent power application process is going to come out on Tuesday to do his first site assessment and measurements so that's rolling too.  I can't move that forward until I have a separate street address but having gone to the County permit office today, I was able to meet my permit tech, Audrey, and she was in a good and playful mood today so we got a lot done!  She's gonna work on my address next week so fingers crossed, we could have permanent power for the shell install.

A great week.   We pour the footings on Tuesday, wohoo!!!

 

Friday, September 22, 2023

We are Rollin'!

Wasting no time!   Jeff, the excavator, created the trench for the foundation footings.  For sure this was the first time he's ever dug in a circle!!


 

The Port-a-Potty is a bit of an eyesore, even with trellising around it...so I decided to start a rotation of embellishments...this is the first installment:
 

 

Next, Steve, the guy who's building the foundation and pouring the concrete got to work and began to lay out the batter boards.  Yes, I'm learning a whole new vocabulary - cuz I needed a few more words in my repertoire!  😂

Given the layout of this foundation, for sure the team's brains hurt with all the calculating and measuring.  I bow to Steve's expertise, it's dazzling to watch in action.


I don't know if I can adequately convey how exciting it was for me to see the first form boards go in...which represent each of the panels in the house.  The first installed was the front door panel - it made it come to life even further.   


From there it went pretty quickly as all 14 panels are like pie pieces...get the center line set, create a grid of snaplines to double, triple and relentlessly check measurements against the plans and you've got it!

It honestly hurt my brain to look at it at this stage...well, it still does but...this is level.  My brain does not see level, yet it is. It reminds me of those old movies in school teaching you about perspective where a person is in a box, that looks like a normal room but when they walk they seem to shrink into a really small sized wall.   Anyway, it's a trick of the eye where there is slope.  Here is what this effort is aimed at creating given the high side of the slope is about 5 feet higher than the downside.

 


 So there'll be a stem wall at the low end that's over 5' high and a shorter one on the high end.

 


That begins to explain these form boards.  



Next they filled the trenches with rebar that is bent into long box shapes.   They have some wicked tools that aid in all that...in the meantime I bought a generator to power all the tools cuz we don't yet have temporary power but I have two great account managers at PG&E hustling on my behalf to get both the temporary power going and the permanent in play - turns out the existing transformer on the property needs to be upgraded so we won't get perm power as quickly as we imagined but it's all good.

The electrical and plumbing subs came to the site yesterday and we worked out the plans for the conduit, chasers and plumbing for wastewater, greywater and water that will go under the slab and be stubbed up through it.  First a waterproof membrane like landscape fabric will go down on the existing base, then the electric conduit will go on that and gravel and perhaps some sand will be used to fill in the circle whilst the pipes are laid into it and drilled out the future stem walls and footings.  All that will be compacted before the slab is poured.  

The current fantasy wish is that we will pour the slab in mid-late October so we can get the shell here in early November.  I love mythical timing.

In other good news, the week ended with the septic plan having been reviewed without pushback and we should have that permit cleared within the week!  There is a bit of a horse race on to get this work done before it begins to rain here.   It's flowing though!

Awesome team, fortunate logistics, and favorable weather.  Life is pretty damn generous.

Friday, September 15, 2023

And so it begins....

 At last, we can do what we've been wanting to do for ages...the team of the excavator, foundation builder and concrete guy, contractors and geo technical engineer showed up at 7:45 am yesterday and began to get real about where, exactly, we are setting this thing up!



Checking, double checking, measuring, adjusting, rethinking, measuring again...fortunately a lot of really competent people were in the mix!  The task was to determine the orientation of the structure so as to set the first panel location to be able to measure from that the rest of the layout.

The excavator needed to do a small cut in the high side of the slope and I have to say, the whole thing looks WAY more slope-y to me now!   Ultimately, we got a circle on the ground that could be dug for foundation footings.

 



 And now, to dig the trench...and the first scoop happened just a few minutes ago!!  Wohoo!



 

 


Monday the foundation builder will start to lay out the form boards and the foundation will come to life!