Follow along on the not so linear or predictable path to the creation of my little forever home!
Tuesday, May 23, 2023
So close.....
Saturday, May 13, 2023
Oops, I did it again!
Ok..so a Britney Spears reference may not be what you expect from me...but it is apt.
Still awaiting the permits...two weeks ago I got an email from the Director of Well and Septic a the Permit Sonoma offices that my building permit application could now move to the review stage - that juncture requires approval from Well & Septic, validating the site can support a wastewater system. Only then will they review any building plans...so a good indicator we are in flow and the permit could get through its bureaucratic gauntlet within a few weeks.
Then, last Friday, I got an email from the person in Well and Septic who will be reviewing the septic permit application, that he won't be able to get to my application for at least two months. They're short staffed. The County does not issue the building permit until the septic permit is "finaled." Suffice it to say, I had a pity party for myself that morning. ππ
After talking with my civil engineer, who was indignant over his longitudinal experience of the process being this slow and rigid, we agreed that the goal at this juncture was to see if the County would be willing to issue the building permit while the septic application is completing its journey through engineering review. The site is approved, the system is straightforward, it's a matter of their backlog.
On Monday I wrote the email below to the Director of Permit Sonoma and the Director of Well and Septic - they are the people who helped me out with the groundwater issue I inquired about last Fall. At least I hoped I wasn't totally anonymous to them:
Hello again…I am writing regarding my building permit application and its status. I am hopeful you can provide a clearer line of sight into where things stand and what can happen next. For reference purposes, my building permit application is BLD22-8614 and the Septic permit application is SEP 23-0080 for an ADU on the property at 4513 W Dry Creek Road.
A little over a week ago I received notification from Nathan that the building permit application was cleared for review. I was grateful to know we had reached that point in the process – while the PRMD portal for tracking the progress of the application is replete with information, it is a bit challenging to decode and truly understand the sequence of steps and interdependencies between them.
The next communication last week was from Chris Luu indicating it will be a couple of months before he will be able to get to the septic permit review. If I understand the PRMD process clearly, regardless of the expediency with which the building permit may be reviewed and readied for issuance, it cannot be released until the septic permit application has been reviewed and approved.
I’m hoping that is not the case. It’ll be five months since the submission of the building permit package at the end of May and while I know your online dashboard should not be considered predictive in a precise way, I have proceeded with project management for my future home with those indicators in mind. My manufactured shell has been constructed and is in storage awaiting the signal from here to send it for assembly and attachment to the slab and foundation and I have a team ready to do site prep. Can it be possible to allow the building permit to be issued (once its review and approval process is complete) so my ADU project can proceed with site prep and readying for the manufactured shell delivery while the septic permit completes its journey through PRMD?
At the time we submitted the building permit application, the timeframe was 12 weeks. We are now at 20 weeks and if the Septic permit process is the driver of timing, another two months plus feels extreme. I requested expediting for both the Septic and Building permits and I do understand that it only happens if there are willing staff to take it on – and I understand the implications of being short staffed as well. I am not asking to be put ahead of any other project in the queue, I simply hope that there is a way for the building permit to be granted acknowledging that the septic permit will come later – which I trust will be a straightforward review since it is neither a complicated or unique system design.
I appreciate whatever favorable consideration you can give to this request, and will likewise be grateful for whatever line of sight you can offer into the process that remains in order for the work on my ADU to be able to begin.
Thank you,
Taya Levine
To my astonishment, I heard back from the Permit Sonoma Director in 15 minutes! His reply was: "We will review this case this today." π
And just two days later, I received this reply:
Ms. Levine,
So I see a couple of things lead to the current circumstance:
Timing of your two submittals – septic system coming two months after the building permit.
Timing of the “clearance” review by Well and Septic of your building application.
For the smoothest development, the infrastructure, namely water and wastewater, are addressed first, then come the structures. Nothing wrong with doing the reverse though considering it appears your engineer was waiting for the wet season to do the percolation testing. Makes sense to keep the architect going while you are waiting for perc test. It’s just we don’t issue the building permit until we know a septic system is viable and code compliant.
I also see the culpability from the County. Had we “screened” the building permit back in January, at least you would have known you needed the septic system prior to the County issuing the building permit and that would have at least provided the expectation.
Imaging the scenario if we allowed a home to be built without water or an operating septic or having a finished home and then finding out septic won’t fit on the parcel. The client would sue the County or file a claim, potentially. So to avoid the potential liability to the County, we set up our procedure of not releasing the building permit until the septic permit is issued.
Given all that, one solution, if you as the owner acknowledges the potential risk and assumes the liability, the County can release the building permit once it is plan reviewed and is ready to be issued.
Granted, I think the risk is reduced in this case because there is a septic application, there is a septic design and there is the site work (soil evaluation and percolation test) on file. Having these reduces the risk of not being able to permit a septic system. The finer points of the septic design have not been fully vetted, so there is still some risk that the County is not willing to assume. My offer is if you assume that risk, we can let the building permit be issued (once it is ready) before the septic system is plan reviewed/issued.
We would hold firm on the occupancy. The ADU could not be occupied until the septic system is permitted, construction and operational.
If acceptable, please reply all, acknowledge the risk of building an ADU without having a permitted septic system and that you realize the County cannot final the ADU or grant occupancy of the ADU until the septic system is operational and the septic permit is finaled.
Sincerely,
Needless to say, I replied all IMMEDIATELY!!!! π€Έπ½♀️ππ½πͺπ½π
Monday, May 1, 2023
Movement and Mastication
Flow is happening more than not at this juncture....
Last week I was notified that a key juncture in the permit application process had been navigated, and the review process is moving forward. Spare you the details but it's a good sign and if you believe the narrative, the permit could be issued within the month.
In the meantime, yesterday was mastication day! If you've never seen a masticator or aren't sure what that is...essentially it's an attachment to big equipment that pulverizes whatever you put it on. Literally. It's a cross between a turbo charged weed whacker and a weed crusher (the other kind π). I have a neighbor who is a big equipment operator and he brought over his rig and we spent a half day, expanding the envelope for the house pad by about 20 feet or so.
Here's what the site was like before we started, note the presence of vegetation in the cleared area, the dense perimeter of vegetation and the overgrown broom (big time fire hazard) along the driveway:
The task was to remove the scrub and broom and poison oak and take out the trees that wouldn't make it or are fire hazards. Here, it's common to eliminate pine trees before they become super mature as they, and their pine cones, are incredibly flammable. The masticator could take down a tree in 90 seconds - saved me some chainsaw activity for sure!
The pulverized litter on the ground will dry up, dessicate and blend in to the mulchy earth over the coming weeks. The site is better prepped for grading now as well. The team who will do site prep and foundation/slab work will be meeting on the site on May 17 to finalize the grading plan. Step by step, it's happening!
It all took about 4 hours, we were done by 12:30. Here's the "after" to compare with the before video above:
Saturday, April 15, 2023
Waiting...nature's in charge
The winter rains here were more than welcomed...they replenished reservoirs, raised the water table to levels that eliminate the need for people (mostly) to truck in water, calmed crunchy nerves related to wildfire risk, and now is producing abundant vegetation the likes of which we haven't seen in quite a while.
What's left behind also includes standing water. And there's a bunch of it on the house site.
I LOVE the sedges that pop up all over the place and hope to preserve and relocate these for planting later - they're here because there's water running through this part of the site. One take on this is - damn, gotta redirect the water - and that's true, french drains under ground will be required to redirect the water to appropriate drainage infrastructure and away from where the foundation will be. Another take on it is, how cool this land is cleansed routinely! π
Waiting for that to dry up a bit more before the next round of vegetation clearing. I shared that a year ago, I did one round of veg clearing and it's time for another around the perimeter of the house pad. Bunches of things sprouted back, defiant at the attempt at their annihilation. It's also going to be helpful not only to remove the broom and pines that are fire fuel, but to eradicate the poison oak and generally enlarge the envelope for the grading work that will be done once the permit is issued. I have a neighbor who has a masticator that we'll use to turn this:
Into more like this:
Just another prep step...doing what we can until we get permission to do everything else.
Still practicing patience. π§π½♀️
Monday, March 20, 2023
Exasperations and Flow
PRMD - if only I could buy a vowel.
PRMD stands for Permits and Resource Management Department - the County's gauntlet for permission to do what you want to do on the land. I could never possibly render the range and litany of stories people like to tell in these parts about this County government department. In moving down this unfamiliar road toward building an ADU in the unincorporated area of the County, many people have cautioned me and/or counseled about how labyrinthian and difficult, if not obstructive, PRMD would be.
Same holds true for PG&E, Pacific Gas and Electric. Part of this project involves applying for power - and there are a range of possibilities for what to request, establish and use between construction power, temporary power, and permanent power. This arena, too, is hallmarked by "it's going to be tough" and "PG&E is going to take forever."
I'm not entirely sure whether these admonitions are an example of "there, there, dear..." thinking and "help" or if they're trying to ensure I am grounded in more reality than magical thinking about how long things will take or if it's just the verbal currency in these trades - the whipping post of the industry - is the bureaucracy. Incompetence, intractability, difficulty, head scratching disconnects between people, the list goes on.
For sure, since this effort went from thinking to doing last year, there have been exasperations. Surprising turns of events, unanticipated obstacles. And if you have known me in my professioal lifespan, you may be aware that there are few bureaucracies I've met that I ever felt daunted by. I have enjoyed many a scenario where I was able to move a situation from stalled, blocked or dysfunctional to flow and results. Kinda took pride in it. This project is giving me plenty of opportunities to apply those experiences anew.
I’ve had victories and been vexed. My first foray resulted in a decision in my favor related to meeting groundwater requirements. My most recent included 24 emails to simply get the cost and payment method for the septic system plan review – they won’t do anything till you pay and trying to find out how much and by what mechanism was, well, successful in the end but really? Same with PG&E, I’ve managed to navigate that system to a scenario where I’ll have metered power within a month of the permit issue – so we’ll build on permitted power – not a year.
You may know I’ve been quite the white knuckler – love me a roller coaster. In this context, not so much, and yet, I ride.