Monday, September 11, 2023

We are GO for launch!

THIS IS WHAT WE HAVE BEEN WAITING FOR!!!!

 

What a long strange summer it's been....I haven't posted since June because, frankly, there was nothing to say while things ran the gauntlet of permit approval.  We got a VERY particular plan reviewer who provided comments and set expectations for additional information back in June.  It took 2 months to prepare the response - meeting their requirements involved special inspections arranged in North Carolina where they had to take some of the manufactured panels out of the storage truck to validate, of all things, nail sheathing.  The first of many inspections to come but fortunately a great team of professionals leaned in, problem solved and got it done.

The building permit was approved on August 30, exactly 8 months from the day we filed the application, and we will start excavating this week!

By way of update, we didn't sit idly by all summer, so let me regale you with what has been done to prepare for the tasks ahead - I didn't want to post about too much of it, waiting for the permit to clear before elaborating on the site prep we went ahead with.

So...thus far, we have trenched (both by hand and equipment) the water line from the water tank down to the house site - which required running the line under two driveways, one unpaved, one paved.  Now have water available there for the site work that will ensue.  We also put in a french drain to move water away from the house site as there is a natural flow of water under this hill that needs mitigating.



A glimpse of the digging from the tank





 The trench down to the site

The other projects we have completed (at least we've taken them as far as they can go before PG&E gets in the mix) is to install the power pole that will be the location of the meter and panel and we trenched conduit down to the house site also - it's ready to go when PG&E activates the power, which should be within the month as I have already qualified for express activation.  We shall see!  It was wild to watch these guys work....as you can tell, I'm geeking out over all of it!  Check out this process of drilling, installing and setting the attachments for PG&E:







 

And, the electric trench and conduit are in - ran that line on the other side of the oak tree...requires not only digging but filling with layers of rock and sand.  



SO...we are READY!

This Thursday and Friday (9/14-15) we will begin to excavate the footings for the foundation and compress the soil for the slab.   Next Monday, the concrete/foundation dude, Steve, will start measuring and laying out the form boards and off we go.

I'm meeting with my contractor on Friday now that we have approved and stamped plans to work with to set the go forward plan so as to reasonably estimate when we can send for the shell.  

It feels great to move from the waiting lane to the doing lane...and I know more waiting will come but really happy to enter this phase!

 

Tuesday, June 13, 2023

Futile Prognostication

I am feeling like a broken record at this point...truly it's a "so close and yet so far" kind of time.

Let's see...so I won the opportunity to get my building permit without the septic permit finalized, so the only thing needed is for PRMD to finish its review processes.  In the past couple of weeks, there have been the usual advances and obstacles.

The remaining processes are finalizing the groundwater issue I wrangled last year - getting everything validated and approved related to that and, the building department's plan check.  Since that was not moving, I wrote an email (a week ago Friday) to the plan checker to whom it seemed to be assigned, asking if there was any way progress could happen within the coming week for a couple of reasons.  I pleaded based on having filed the application in December, and being oh so ready to put shovels in the ground but moreover, my architect informed me last week he'd be away June 10-30!  Did not see that coming, and really hoped not to bump into July for getting started...if possible. Basically we had a week to turn this all around...never really thought of myself as someone with an active fantasy life but, if there ever was a moment to check connection with reality, this was one of them.

I got an auto-reply message that he was out of the office until Monday...that kinda put me over the edge that week - so many roller coaster dynamics, I just didn't have any more resiliency in me and kinda melted down - surrender is more like it.   Then, at 9:15 pm on Friday night, I got an email from the plan checker, who happens to be the Director of the department, who said "Hi, Taya.  I can get to that next week, no problem."  Seriously, at 9:15 pm he takes the time to reach out with humanity and reassurance?!!!  Big time exhale.

He did his review over the weekend, provided the comments on Monday - and they were voluminous.   There are requirements to have an independent third party validate the CalGreen energy calculations - did not know that.  Managed to find someone to turn that around in 24 hours, thankfully.  They expected more info on the solar plans - all new home construction in CA is required to have solar - but we intend to do that next year, after the house is up and running, and can - but more commentary on that is required.  They required new structural calculations from the shell builder, Deltec, and they required a much more exhaustive soils report/analysis from my brother in law the GeoTech engineer.  Once those are presented back to my architect, he has to recalculate the foundation plans...and so it goes.

NOTHING about this process is straightforward, swift or reliable.  So, everyone's leaning in to deliver quickly, my architect is staying attentive while away and who knows...I've given up entirely on attempting to predict timeframes, hence the title off this post.

In the meantime, we continue to do what can be done - and here's the latest.  You might wonder how many times you can look at a bare piece of land, but these shifts in the space are quite dramatic.  The site is scraped, and the circle for the structure is clearly visible as is the center pole.

 

It's kind of wild...I can visualize and "feel" the space so much more...it has a spatial dimension to it now that's palpable.  I haven't spent much time just walking it, sitting in it, and I will - this just got done on Saturday.  Feels really good though....

So, at the risk of being a broken record, we are, so so close.


Tuesday, May 23, 2023

So close.....

Inching closer...after the PRMD decision, I went down to talk with a Permit Tech to understand what remains or if there's anything in the way of getting to permit issuance.  When she looked at my application, she extolled "This is an ADU?  The new laws say this should have been expedited from the beginning - we're supposed to be creating more housing!" and with that she looked at the status of things and wrote to the head of the Building Department and the Ombudsman prompting attention and response.  Another bit 'o support for which I'm grateful.  She also said "You should have this permit within a week!"  Still practicing patience.
 
In the meantime, we continue to do what can be done until we get permission to do everything else.   Had a meeting on the site with all the trades implicated in site prep and foundation.  The first visual indicator there'll be work on the land (beyond it being prepped, of course) is this:
 
 

 
 
The men who are going to prepare this site and ensure the house is securely on the land are a great team.  I feel fortunate to have such experienced, competent people of character helping my home to become.  I had these made for every person who works on the house and gave them out to this core team at the meeting:
 
 
 
 
 
That meeting was super productive, we got a solution for the grading and determined concrete patio is the best way to go.  Just need a small additional retaining wall to support everything and we're good to go.  Grateful for all of the problem solving collaboration that went on between everyone!
 
Next, I strapped on a tank to spray the young Broom coming back up post-mastication.  Lots of things to do to maintain this raw land!!!  Yes, this is my life:
 
 


I check the PRMD website every day, making sure we're on whatever the comments or issues raised are as quickly as we can be.   In the meantime, some fun things....
 
Buzz and Jean got a Club Car!  They're going to use it to go easily back and forth between our houses and it even will make it easier to do a mail run at a whim!  A new toy definitely brings out the kid in all of us:
 
 

 
And when he took me for a spin down the driveway, he pointed to one of his uniquely trained Zinfandel vines that is no longer producing.  It's so sculptural..and he said "that's your new hot tub towel rack!"  So yes, he's going to drill a hole in the base, mount it on a pole, et voilĂ !  Cuz that's how we roll....so cool.
 
 

 

Stay tuned!